Compare bookings with task assignments per project
Project management and accountingInquiries and reportsResource scheduling inquiries
PSAResAssignAnalysis_Project
Used by
Project manager, Resource manager
Business process
Plan projects
Menu item
PSAResAssignAnalysis_Project
Main table
PSATmpResourceAssignmentAnalysis
Setup steps
1 on this page
Show what matters for
SETUP GUIDEHow to set it up8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
An inquiry that shows, per project, the type, name, staffing status, scheduled start and end dates and the hard-booked and hard-assigned hours for a date range.
What you do here
Use it to answer 'which projects are fully staffed, and where do bookings and task assignments not agree?'
Example
For Q4 the BEAT project manager sees PRJ-0042 with 480.00 hours hard-booked but only 400.00 hours hard-assigned to tasks, so 80.00 booked hours have no task yet.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
Setup steps on this page
Compare bookings with task assignments per project
Spot projects where booked hours and assigned hours differ.
Steps from Microsoft
Go to Project management and accounting > Inquiries and reports > Resource scheduling inquiries > Resource reservation analysis - Project.
Enter the Start date and End date, and select a Project ID or leave it blank to compare all projects.
Compare hard-booked with hard-assigned hours; a gap means bookings with no task or tasks with no booking.
Select the project row and then Project to fix the team or the work breakdown structure.
Hours assigned to tasks in the work breakdown structure.Checked in Dynamics 365
400.00
Schedule start date / Schedule end date
The scheduled dates of the project.Checked in Dynamics 365
2026-10-01 to 2026-12-31
Common errors and fixes
Message
What to do
A new project shows no hours.
Hours appear only after resources are booked on the project team; a work breakdown structure with roles alone reserves planned resources. Microsoft Learn
Enter the period and compare hard-booked with hard-assigned per project.Bookings reserve people for the project; assignments put them on tasks. Only together do they make a workable plan.
On the live system, Resource manager maintains this page and Project manager views it.
Checked in Dynamics 365
Solution architect
5Design impact
Shared or per company
Per company for the projects, but capacity comes from resource calendars that the capacity batch job fills across all companies, so a resource lent by another legal entity can show here. Microsoft Learn
Can it be undone
Reversible: Reading the page changes no data.
If you change it later
The page recalculates from bookings, assignments and calendar capacity each time you search; after a calendar change, run the capacity synchronization again or capacity stays at the old value. Microsoft Learn
Technical architect
6Technical
Menu item
PSAResAssignAnalysis_ProjectChecked in Dynamics 365
Form
PSAResourceAssignmentAnalysisChecked in Dynamics 365
Table
PSATmpResourceAssignmentAnalysisShown as “Hold information for resource assignment analysis” in Record infoChecked in Dynamics 365
To set it up or change itResource manager ProjResourceManagerTo use itProject manager ProjProjectManagerGive people one of these roles. On this system, 2 roles can open this page.Checked in Dynamics 365
Actions on the page
Options: Personalize, Page options, ShareChecked in Dynamics 365
Load order: Resource reservation analysis - Project has no data entity in Data management: it fills a temporary table when you search. Reservations come from bookings and assignments on project teams (ResBooking and ResAssignment), created by staffing projects; capacity comes from the calendar synchronization job.Microsoft Learn
Checked in a working Dynamics 365 system, version 10.0.49: the menu item, form, table and security, the page.