Inquiry page · Project management and accounting

Resource reservation analysis - Project

An inquiry that shows, per project, the type, name, staffing status, scheduled start and end dates and the hard-booked and hard-assigned hours for a date range.

Used by
Project manager, Resource manager
Business process
Plan projects
Menu item
PSAResAssignAnalysis_Project
Main table
PSATmpResourceAssignmentAnalysis
Setup steps
1 on this page
Show what matters for
PAGE GUIDEWhat the page does and how to use it8 sections. Choose a role to highlight what matters to you.
Everyone

1What it is and why

What it isAn inquiry that shows, per project, the type, name, staffing status, scheduled start and end dates and the hard-booked and hard-assigned hours for a date range.
What you do hereUse it to answer 'which projects are fully staffed, and where do bookings and task assignments not agree?'
ExampleFor Q4 the BEAT project manager sees PRJ-0042 with 480.00 hours hard-booked but only 400.00 hours hard-assigned to tasks, so 80.00 booked hours have no task yet.
Resource reservation analysis - Project page in Dynamics 365
The page in Dynamics 365. page title tab to open what to set or check
Functional consultant · Solution architect

2Where it fits

Business processPlan projects
Menu pathProject management and accounting › Inquiries and reports › Resource scheduling inquiries › Resource reservation analysis - Project
Set up firstAll projects Microsoft Learn
Used next byResource fulfillment Microsoft Learn
Related pagesResource reservation analysis - Resource Microsoft Learn
End user · Functional consultant

3How to do it

About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.

Setup steps on this page

Compare bookings with task assignments per project

Spot projects where booked hours and assigned hours differ.

Steps from Microsoft

  1. Go to Project management and accounting > Inquiries and reports > Resource scheduling inquiries > Resource reservation analysis - Project.
  2. Enter the Start date and End date, and select a Project ID or leave it blank to compare all projects.
  3. Compare hard-booked with hard-assigned hours; a gap means bookings with no task or tasks with no booking.
  4. Select the project row and then Project to fix the team or the work breakdown structure.

Source: Microsoft Learn

Fields on the page

FieldWhat it meansExample
Staffing statusHow far the project is staffed with resources.Checked in Dynamics 365
Hard-bookedHours booked on the project team.Microsoft Learn 480.00
Hard-assignedHours assigned to tasks in the work breakdown structure.Checked in Dynamics 365400.00
Schedule start date / Schedule end dateThe scheduled dates of the project.Checked in Dynamics 3652026-10-01 to 2026-12-31

Common errors and fixes

MessageWhat to do
A new project shows no hours.Hours appear only after resources are booked on the project team; a work breakdown structure with roles alone reserves planned resources. Microsoft Learn

Test checklist

  1. Book a resource for 40.00 hours on PRJ-0042.
  2. Assign 32.00 of those hours to a task.
  3. Run the analysis for the week.
  4. Check 40.00 hard-booked and 32.00 hard-assigned.

Source: Microsoft Learn

Functional consultant

4Setup decisions

Setup stepRecommended value and whyDecision, common mistake and test
Compare bookings with task assignments per projectEnter the period and compare hard-booked with hard-assigned per project.Bookings reserve people for the project; assignments put them on tasks. Only together do they make a workable plan.Do projects book resources before or after the WBS is drafted?Reading hard-booked hours as the planned effort; the work breakdown structure assignments are the plan.Test: Booked versus assigned

Feature management and licence

Licence or add-inOn the live system, Resource manager maintains this page and Project manager views it.

Checked in Dynamics 365

Solution architect

5Design impact

Shared or per companyPer company for the projects, but capacity comes from resource calendars that the capacity batch job fills across all companies, so a resource lent by another legal entity can show here. Microsoft Learn
Can it be undoneReversible: The inquiry changes no data. Microsoft Learn
If you change it laterThe page recalculates from bookings, assignments and calendar capacity each time you search; after a calendar change, run the capacity synchronization again or capacity stays at the old value. Microsoft Learn
Technical architect

6Technical

Menu itemPSAResAssignAnalysis_Project Checked in Dynamics 365
FormPSAResourceAssignmentAnalysis Checked in Dynamics 365
TablePSATmpResourceAssignmentAnalysisShown as “Hold information for resource assignment analysis” in Record infoChecked in Dynamics 365
Who can open itPrivilegesResource manager ProjResourceManagerMaintain project schedules ProjSchedulingMaintainMaintain project schedules ProjSchedulingViewDutiesInquire into project schedule master ProjProjectScheduleMasterInquireMaintain project schedule master ProjProjectScheduleMasterMaintainResource manager ProjResourceManager
2 security rolesProject manager ProjProjectManagerResource manager ProjResourceManager
Checked in Dynamics 365
Roles to set it up and use itTo set it up or change itResource manager ProjResourceManagerTo use itProject manager ProjProjectManagerGive people one of these roles. On this system, 2 roles can open this page.Checked in Dynamics 365
Actions on the pageOptions: Personalize, Page options, ShareChecked in Dynamics 365
Developer

7Developer

Open it by URLhttps://<your-environment>/?mi=PSAResAssignAnalysis_Project
Data migrationLoad order: Resource reservation analysis - Project has no data entity in Data management: it fills a temporary table when you search. Reservations come from bookings and assignments on project teams (ResBooking and ResAssignment), created by staffing projects; capacity comes from the calendar synchronization job.Microsoft Learn