Setup step on the All CAPA activities due this week page · Common

Work CAPA activities from All CAPA activities due this week

Find and finish CAPA activities so cases can move through their stages.

Used by
CAPA administrator, CAPA updater
Business process
Use corrective and preventative (CAPA) management module to enter and record details about CAPA cases in Dynamics 365 Supply Chain Management
Menu item
QMSActivitiesListPageAllDueThisWeek
Main table
smmActivities
Data entity
None for this page's own settings
Setup steps
1 on this page
Show what matters for
SETUP GUIDEHow to set it up8 sections. Choose a role to highlight what matters to you.
Everyone

1What it is and why

What it isA list page that shows corrective and preventive action (CAPA) activities for all users, filtered to activities that are due in the current week. Activities are the tasks inside each stage of a CAPA case process.
What you do hereUse this page to find the CAPA activities that need work, open an activity to enter notes and information, and mark it as complete so the case can move to its next stage.
ExampleFor example, BEAT's quality manager checks All CAPA activities due this week on Monday: 9 activities fall due, including the containment check for case CAPA-000015, and assigns cover for a worker on leave.
All CAPA activities due this week page in Dynamics 365
The page in Dynamics 365. page title tab to open what to set or check
Functional consultant · Solution architect

2Where it fits

End user · Functional consultant

3How to do it

About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.

Setup steps on this page

Work CAPA activities from All CAPA activities due this week

Find and finish CAPA activities so cases can move through their stages.

Steps from Microsoft

  1. Go to Common > Common > Activities > CAPA activities > All CAPA activities due this week.
  2. Use All CAPA activities due this week to see the CAPA activities of all workers that fall due in the current week.
  3. Check who owns each one and whether they are available this week.
  4. Select Set as complete on the Activity tab when the work is done; when all mandatory activities of the stage are closed, change the case's stage.

Source: Microsoft Learn

Fields on the page

FieldWhat it meansExample
Activity numberThe number of the CAPA activity.Checked in Dynamics 365BEAT-000011
Start dateThe date the activity starts.Checked in Dynamics 36511/09/2026
PurposeWhat the activity asks for, such as Identify the problem.Microsoft Learn Identify the problem
ResponsibleThe worker or worker group the CAPA process assigned.Microsoft Learn
ClosedMarks the CAPA activity as completed.Microsoft Learn Yes after Set as complete.

Common errors and fixes

MessageWhat to do
The case can't move to the next stageClose every mandatory activity of the current stage first. Microsoft Learn

Test checklist

  1. Create a CAPA case with a CAPA process and set it to In process.
  2. Give an activity a due date in this week and check that it is listed.
  3. Open the activity, enter notes and select Set as complete.
  4. Check that the activity leaves or stays on this list as its filter says, and that the case can change stage.

Source: Microsoft Learn

Functional consultant

4Setup decisions

Setup stepRecommended value and whyDecision, common mistake and test
Work CAPA activities from All CAPA activities due this weekReview this list by Responsible at the start of each weekIt shows the whole quality team's deadlines for the week.Who is assigned CAPA activities?Treating it as overdue work: late activities are on All CAPA activities past due.Test: CAPA activity on All CAPA activities due this week

Feature management and licence

Feature to turn onAdvanced quality management (Mandatory, on by default)
Licence or add-inOn the live system, these roles can open the page: CAPA updater, CAPA administrator.

Microsoft Learn

Solution architect

5Design impact

Shared or per companyPer company: CAPA activities belong to CAPA cases of the legal entity (the Activities entity is not shared). Checked in Dynamics 365
Can it be undoneHard to reverse: Closing the last mandatory activity lets the case change stage, which can't be reversed.
If you change it laterClosing the last mandatory activity of a stage lets the case move to its next stage, which can't be undone. Microsoft Learn
Technical architect

6Technical

Menu itemQMSActivitiesListPageAllDueThisWeek Checked in Dynamics 365
FormsmmActivities Checked in Dynamics 365
TablesmmActivitiesShown as “ACTIVITIES” in Record infoKey field: ActivityNumberChecked in Dynamics 365
Data entitiessmmActivitiesEntityActivities (the activity records; CAPA activities are generated by the CAPA process, not loaded) Microsoft data model
Who can open itPrivilegesView my CAPA activities QMSSmmActivitiesListPage_MyActivityViewMaintain my CAPA activities QMSSmmActivitiesListPage_MyActivMaintainDutiesMaintain CAPA activities QMSsmmActivitiesMaintain
2 security rolesCAPA administrator QMSCAPAAdministratorCAPA updater QMSCAPAUpdater
Checked in Dynamics 365
Roles to set it up and use itTo set it up or change itCAPA updater QMSCAPAUpdaterCAPA administrator QMSCAPAAdministratorGive people one of these roles. On this system, 2 roles can open this page.Checked in Dynamics 365
Actions on the pageActivity: Maintain, Set up, Attachments(Action Pane without tabs): New, DeleteChecked in Dynamics 365
Developer

7Developer

Open it by URLhttps://<your-environment>/?mi=QMSActivitiesListPageAllDueThisWeek
Data migrationsmmActivitiesEntity (Activities): loaded for each company.Load order: CAPA activities are generated by the CAPA process when a case reaches a stage; migrate open CAPA cases and let the process generate the activities.Load first: CAPA cases, CAPA process templatesMicrosoft Learn
Everyone

8Sources

To cite this step: CMN-CAPAACT-050, Work CAPA activities from All CAPA activities due this week. Beyond ERP Atlas Hub, 2026-11-11. https://www.beyonderp.cloud/atlas/step/CMN-CAPAACT-050