Project management and accountingInquiries and reportsForecast transactions reports
output:ProjListBudgetID
Business process
Analyze project performance
Menu item
output:ProjListBudgetID
Setup steps
1 on this page
Show what matters for
SETUP GUIDEHow to set it up8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
A report that lists forecast transactions of one forecast model grouped by resource or item: forecast hours per worker and forecast quantities per item. The report design is ProjListBudget.
What you do here
Use it to answer 'how many hours do we expect from each person, and how many units of each item?' for staffing and purchasing plans.
Example
The BEAT project assistant runs model FC-2026 for December with Hour and Item on and sees R-0105 forecast for 168.00 hours, 8.00 above capacity, and item CABLE-10 for 120.00 units, which goes to purchasing.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
When to run it
When to run it
Before staffing and purchasing plans for the next months.
How often
Monthly.
What the output shows
Forecast hours per worker and quantities per item for one model. The report design is ProjListBudget.
Which project types to include; the dialog toggles Time and material, Fixed-price, Investment, Internal and cost (Internal and Cost project types) and Time.Checked in Dynamics 365
Time and material, Fixed-price, Investment
Include transaction types
Hour and Item carry the worker or item on forecast lines.Checked in Dynamics 365
Hour, Item
(Project date) From date / To date
The range of forecast project dates; forecasts have no fiscal period.Microsoft Learn
1 November to 31 December
(Ledger date) From date / To date
Limits the report to transactions within a range of ledger dates.Microsoft Learn
Project statement
The statement the amounts follow; the dialog suggests Profit and loss.Checked in Dynamics 365
Profit and loss
Forecast model
The model whose forecast lines the report lists; a submodel shows only that part of the forecast. Budgets store their original and remaining amounts in two models, so budget data shows here too.Microsoft Learn
Choose the model, turn on Hour or Item, and set the months you plan for.Forecast lines can carry a worker, a role or neither; only lines with a worker show per person.
On the live system, Project assistant is the role that runs this report. Feature management controls whether this report skips the reporting framework's transaction scope (ProjSSRSSkipReportTransactionFeature), which helps large runs.
Per company: forecast models are shared setup, but the forecast lines belong to the projects of the current legal entity. Microsoft data model
Can it be undone
Reversible: Reading the page changes no data.
If you change it later
The report shows the model as it is when you run it; forecast reduction and edits change it without history, so keep a copy of the original model for comparisons. Microsoft Learn
Technical architect
6Technical
Menu item
output:ProjListBudgetIDChecked in Dynamics 365
Form
SysOperationTemplateFormChecked in Dynamics 365
Roles to set it up and use it
To use itProject assistant ProjProjectClerkGive people one of these roles. On this system, 1 role can run this page.Checked in Dynamics 365
Load order: The Resource/item forecast transactions report has no data entity in Data management: it reads forecast lines. Load the forecasts with the forecast entities (for example ProjForecastEmplEntity for hours) and run the report to compare totals per model.Microsoft data model
Checked in a working Dynamics 365 system, version 10.0.49: the menu item, form, table and security, the page.
To cite this step: PM-RA-360, Compare forecast hours per person with capacity. Beyond ERP Atlas Hub, 2026-11-11. https://www.beyonderp.cloud/atlas/step/PM-RA-360