Project management and accountingPeriodicRevenue recognition
action:ProjControlPeriod_CalculateV2
Business process
Manage project financials
Menu item
action:ProjControlPeriod_CalculateV2
Setup steps
1 on this page
Show what matters for
SETUP GUIDEHow to set it up8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
A periodic job that recalculates the open revenue recognition records of a period for many projects at once, optionally including the cost side.
What you do here
Use it after Create revenue recognition, and again whenever costs or forecasts change before posting.
Example
After a late vendor invoice of 4,800.00 is posted to PRJ-0042 on 11/02/2026, the project accountant recalculates October for period code MONTH: the completion of PRJ-0042 moves from 60.00 to 63.00 percent before posting.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
When to run it
When to run it
After Create revenue recognition, and again after any cost or forecast change before posting.
How often
At least once per period, plus reruns after corrections.
Batch settings
Run in the background for all projects of the period code.
What the output shows
Recalculated completion percentages and WIP or accrual amounts on the open records.
Recalculate after the last cost posting of the period, with Update cost recognition on.Late costs change the completion percentage and so the recognized revenue.
Load order: Calculate revenue recognition has no data entity in Data management, and the revenue recognition period table (ProjControlPeriodTable) has none either. Migrate WIP and accrual balances, then create revenue recognition in the target system from the first open period.Microsoft data model