Project management and accountingPeriodicForecasts
action:ProjForecastBudgetCopy
Business process
Plan projects
Menu item
action:ProjForecastBudgetCopy
Setup steps
1 on this page
Show what matters for
SETUP GUIDEHow to set it up8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
A periodic job that copies the forecast transactions of one forecast model into another forecast model, for the transaction types and dates you choose.
What you do here
Use it to build a new forecast model from an existing one, for example a copy that forecast reduction can reduce while the original forecast stays for reporting.
Example
BEAT's forecast model FC-2026 holds 1,240.00 forecast hours and 48,600.00 of expenses for PRJ-0042. The project manager copies the hour and expense transactions to FC-2026-RED, which forecast reduction then reduces, while reports keep showing the original FC-2026 figures.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
When to run it
When to run it
When a forecast model is created from an existing one, or before forecast reduction starts.
How often
On demand, when a forecast model is created or revised.
Batch settings
Run in the background when many projects have forecasts in the model.
What the output shows
Forecast transactions of the chosen types and dates in the To forecast model. Running it twice into the same model duplicates the lines.
The transaction types (hour, expense, item, fee, on-account) to copy to the other forecast model.Microsoft Learn
Hour and Expense
From date
With To date, the date range of the forecast transactions to copy.Microsoft Learn
01/01/2026 to 12/31/2026
From forecast model
The forecast model to copy from; To forecast model is the model that receives the copy.Microsoft Learn
From FC-2026 to FC-2026-RED
Common errors and fixes
Message
What to do
The To forecast model shows double amounts.
The job was run twice into the same model. Remove the copy with Delete forecasts on the To model for the same types and dates, then copy once. Microsoft Learn
Test checklist
Total the hour forecast of PRJ-0042 in FC-2026 (for example 1,240.00 hours).
Copy hours for 2026 to FC-2026-RED.
Total the hour forecast of PRJ-0042 in FC-2026-RED: 1,240.00 hours.
On the live system, Project manager, Project accountant and Project assistant use this page.
Checked in Dynamics 365
Solution architect
5Design impact
Shared or per company
Per company: forecast transactions and forecast models belong to the legal entity you run it in. Microsoft data model
Can it be undone
Reversible: Delete forecasts removes the copied lines.
If you change it later
Adds forecast transactions to the To model. Reports, cost control and forecast reduction that use that model change; the From model isn't changed. Microsoft Learn
Technical architect
6Technical
Menu item
action:ProjForecastBudgetCopyChecked in Dynamics 365
Form
DialogChecked in Dynamics 365
Roles to set it up and use it
To use itProject manager ProjProjectManagerProject accountant ProjProjectAccountantProject assistant ProjProjectClerkGive people one of these roles. On this system, 3 roles can run this page.Checked in Dynamics 365
Load order: Copy forecasts has no data entity in Data management: it is a periodic job and keeps no records of its own. Load forecast lines with the forecast entities (for example ProjForecastEmplEntity for hour forecasts) and copy models in the target system.Load first: ProjForecastEmplEntityMicrosoft data model