Setup step on the Mass transfer page · Fixed assets

Move assets to new dimensions

Transfer the financial dimensions of many asset books at once.

Business process
Maintain fixed assets
Menu item
action:AssetTransferMass
Setup steps
1 on this page
Show what matters for
SETUP GUIDEHow to set it up8 sections. Choose a role to highlight what matters to you.
Everyone

1What it is and why

What it isA periodic job that transfers any number of fixed assets to new financial dimension values in one run, using query criteria to pick the assets.
What you do hereUse this periodic task to move the financial values of many assets to a new department, cost center or other dimension at the same time.
ExampleFor example, after a reorganization, assets 180 through 950 in group FURN move from department 022 to department 024 on 1 July in one run, instead of one transfer per asset.
Mass transfer page in Dynamics 365
The page in Dynamics 365. page title tab to open what to set or check
Functional consultant · Solution architect

2Where it fits

End user · Functional consultant

3How to do it

About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.

When to run it

When to run itWhen an organization change moves many assets to a new department, cost center or other dimension at once.
How oftenOn demand, after each reorganization.
Batch settingsSchedule it on the Batch tab for large selections; assets are processed in groups.
What the output showsTransfer transactions that move the asset books to the new financial dimension values on the transfer date. An asset that wasn't transferred was in a group in which another asset failed.

Source: Microsoft Learn

Setup steps on this page

Move assets to new dimensions

Transfer the financial dimensions of many asset books at once.

Steps from Microsoft

  1. Go to Fixed assets > Periodic tasks > Mass transfer.
  2. In Transfer date, enter the date for the accounting transactions that the transfer creates, and add Transfer comments if needed.
  3. In Transfer to financial dimensions, select the new dimension values. Values you leave blank are transferred as blank if the account structure allows it.
  4. Select Select and enter the criteria for the assets to move, for example one fixed asset group or the old department.
  5. Run the transfer, then open the fixed asset transactions of a few assets to check the new dimension values.

Source: Microsoft Learn

Fields on the page

FieldWhat it means
Transfer dateThe date used for the accounting transactions that the transfer creates.Microsoft Learn
Transfer to financial dimensionsThe financial dimension values the selected asset books move to; every dimension value changes, including those you leave blank if the account structure allows blanks.Microsoft Learn

Common errors and fixes

MessageWhat to do
A dimension became blank after the transferAll dimension values change in a transfer, also the blank ones. Enter every value the books must keep. Microsoft Learn

Test checklist

  1. Selected assets show the new dimension values on their books.
  2. Transfer transactions are dated on the transfer date.
  3. No asset group was skipped because of an error.

Source: Microsoft Learn

Functional consultant

4Setup decisions

Setup stepRecommended value and whyDecision, common mistake and test
Move assets to new dimensionsEnter every dimension value the books must have, run a test on a few assets first, and use a transfer date at the start of a period.All dimension values change when a transfer occurs, whether a value is entered or left blank.Transfer or reclassify?Leaving dimensions blank that should stay.Test: Dimensions moved

Feature management and licence

Licence or add-inFixed assets is part of Dynamics 365 Finance. Fixed asset accountants run transfers after a reorganization. On this system the roles that open the page include Accounting supervisor, Accountant, Rental manager, Rental purchasing manager. No Feature management feature needs to be turned on for this page.

Checked in Dynamics 365

Solution architect

5Design impact

Shared or per companyPer company. Microsoft Learn
Can it be undoneHard to reverse: A posted transfer is undone only by transferring back.
If you change it laterAssets are processed in groups of about 200; if one asset in a group fails, none of the assets in that group are transferred. Microsoft Learn
Technical architect

6Technical

Menu itemaction:AssetTransferMass Checked in Dynamics 365
FormSysOperationTemplateForm Checked in Dynamics 365
Roles to set it up and use itTo use itAccounting supervisor LedgerAccountingSupervisorAccountant LedgerAccountantRental manager RentalManagerRental purchasing manager RentalPurchasingManagerGive people one of these roles. On this system, 4 roles can run this page.Checked in Dynamics 365
Developer

7Developer

Open it by URLhttps://<your-environment>/?mi=action:AssetTransferMass
Data migrationLoad order: Mass transfer has no data entity in Data management, so it can't be loaded from a file or a configuration template. The report stores nothing of its own: it reads the posted fixed asset data, so migrate the assets, books and transactions and run it again in the new environment.Microsoft Learn
Everyone

8Sources