Setup step on the Parameters by site page · Cost management
Set up Parameters by site
Use this page to override company-wide manufacturing accounting settings for a specific site, such as whether picking list and report as finished journals for production orders post to the general ledger.
Inventory accountant, Inventory accountant clerk, Accounting manager and 2 more roles
Business process
Define costing policies
Menu item
CostProdParametersSite
Main table
ProdParametersDim
Data entity
ProdSiteSpecificProductionControlParametersEntity
Setup steps
1 on this page
Show what matters for
SETUP GUIDEHow to set it up8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
A setup page where you set production control parameters for an individual site, so that the site can use settings that differ from the company-wide Production control parameters.
What you do here
Use this page to override company-wide manufacturing accounting settings for a specific site, such as whether picking list and report as finished journals for production orders post to the general ledger.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
Setup steps on this page
Set up Parameters by site
Use this page to override company-wide manufacturing accounting settings for a specific site, such as whether picking list and report as finished journals for production orders post to the general ledger.
How to use it
Go to Cost management > Manufacturing accounting policies setup > Parameters by site.
On the Overview tab, select New to add a row.
In the Site field, select the site that needs its own settings.
Select the Manufacturing accounting tab and set the parameters for the selected site.
Select Save.
Source: Checked in Dynamics 365
Fields on the page
Field
What it means
Table column
Post picking list in ledger
Controls whether the picking list journal for a production order posts to the general ledger. The company-wide setting can be overridden for the site on this page.Microsoft Learn
PostPickList
Post report as finished in ledger
Controls whether the report as finished journal for a production order posts to the general ledger. The company-wide setting can be overridden for the site on this page.Microsoft Learn
PostReportedFinished
Test checklist
Create a site record and select Post picking list in ledger and Post report as finished in ledger.
Post a picking list journal for a production order at that site.
Check a voucher posts to Estimated cost of materials consumed and Estimated cost of materials consumed, WIP.
Report the order as finished and check the voucher on Estimated manufactured cost and Estimated manufactured cost, WIP.
Repeat at a site without the options and check no WIP voucher is created.
For sites that use WIP accounting, select Post picking list in ledger and Post report as finished in ledger; add a site record only where the site must differ from Production control parameters.Picking list and report as finished journals post WIP to the ledger only when these options are selected; the site record overrides the company-wide setting for that site.
Selecting the options but leaving Post physical inventory off on the item model group, or leaving the Estimated cost of materials consumed / Estimated manufactured cost accounts blank. Then no WIP voucher is posted.Test: Site override posts WIP for picking list
Reversible: The options are checked when each journal is posted, so a change affects journals posted afterwards; journals already posted keep their vouchers.
Technical architect
6Technical
Menu item
CostProdParametersSiteChecked in Dynamics 365
Form
ProdParametersChecked in Dynamics 365
Table
ProdParametersDimShown as “PRODUCTION PARAMETERS BY SITE” in Record infoKey field: InventDimIdChecked in Dynamics 365
Data entities
ProdSiteSpecificProductionControlParametersEntityProduction control parameters by site Microsoft data model
Who can open it
PrivilegesMaintain costing parameters CostParametersMaintainView costing parameters CostParametersViewMaintain production parameters by site ProdParametersSiteMaintainView parameters by site ProdParametersSiteViewDutiesInquire into costing policies CostPoliciesInquireMaintain costing policies CostPoliciesMaintainInquire into production policies ProdProductionPoliciesInquireEnable production process ProdProductionProcessEnable5 security rolesInventory accountant InventCostAccountantInventory accountant clerk InventCostCostClerkAccounting manager LedgerAccountingManagerProduction manager ProdProductionManagerProcess engineering manager RouteProcessEngineeringManagerChecked in Dynamics 365
Roles to set it up and use it
To set it up or change itAccounting manager LedgerAccountingManagerProduction manager ProdProductionManagerProcess engineering manager RouteProcessEngineeringManagerTo use itInventory accountant InventCostAccountantInventory accountant clerk InventCostCostClerkGive people one of these roles. On this system, 5 roles can open this page.Checked in Dynamics 365
ProdSiteSpecificProductionControlParametersEntity (Production control parameters by site): loaded for each company, in Microsoft's default template 410 - Production control.Load order: Microsoft's default template 410 - Production control loads Production control parameters by site at execution unit 1, level 410, sequence 70. Lower levels load first, and entities at the same level load in sequence order.Load first: the default templates at lower levels (System setup to Transportation management)Microsoft Learn