An inquiry that shows, per resource category and role, the capacity, hard-reserved and soft-reserved hours, unscheduled hours and utilization for a date range.
Project management and accountingInquiries and reportsResource scheduling inquiries
PSAResAssignAnalysis_ResCategory
Used by
Project manager, Resource manager
Business process
Plan projects
Menu item
PSAResAssignAnalysis_ResCategory
Main table
PSATmpResourceAssignmentAnalysis
Setup steps
1 on this page
Show what matters for
PAGE GUIDEWhat the page does and how to use it8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
An inquiry that shows, per resource category and role, the capacity, hard-reserved and soft-reserved hours, unscheduled hours and utilization for a date range.
What you do here
Use it to answer 'do we have enough people in each role for the work we have reserved?' for hiring and subcontracting decisions.
Example
For the first quarter the BEAT resource manager sees role CONSULT with 1,440.00 hours capacity and 1,620.00 hours reserved, while role DEV has 320.00 unscheduled hours, so two consulting tasks are subcontracted.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
Setup steps on this page
Check capacity per role
Compare the capacity of each role with the hours reserved for it.
Steps from Microsoft
Go to Project management and accounting > Inquiries and reports > Resource scheduling inquiries > Resource reservation analysis - Role.
Enter the Start date and End date for the planning horizon.
Filter the list on the roles you plan for and compare Capacity with hard- and soft-reserved hours.
For roles above 100 percent, raise resource requests or plan subcontractors; for roles with unscheduled hours, offer them to new projects.
Use a planning horizon of at least one quarter and compare hard-reserved hours with capacity per role.Roles let you reserve before you know who will do the work, so role totals show demand earlier than named bookings.
On the live system, Resource manager maintains this page and Project manager views it.
Checked in Dynamics 365
Solution architect
5Design impact
Shared or per company
Per company for the projects, but capacity comes from resource calendars that the capacity batch job fills across all companies, so a resource lent by another legal entity can show here. Microsoft Learn
The page recalculates from bookings, assignments and calendar capacity each time you search; after a calendar change, run the capacity synchronization again or capacity stays at the old value. Microsoft Learn
Technical architect
6Technical
Menu item
PSAResAssignAnalysis_ResCategoryChecked in Dynamics 365
Form
PSAResourceAssignmentAnalysisChecked in Dynamics 365
Table
PSATmpResourceAssignmentAnalysisShown as “Hold information for resource assignment analysis” in Record infoChecked in Dynamics 365
To set it up or change itResource manager ProjResourceManagerTo use itProject manager ProjProjectManagerGive people one of these roles. On this system, 2 roles can open this page.Checked in Dynamics 365
Load order: Resource reservation analysis - Role has no data entity in Data management: it fills a temporary table when you search. Reservations come from bookings and assignments on project teams (ResBooking and ResAssignment), created by staffing projects; capacity comes from the calendar synchronization job.Microsoft Learn