Set the ledger dates and layout for Ledger reconciliation - WIP
Project management and accountingInquiries and reportsGeneral ledger reconciliation reports
output:ProjListLedgerReconWIP
Business process
Manage project financials
Menu item
output:ProjListLedgerReconWIP
Setup steps
1 on this page
Show what matters for
SETUP GUIDEHow to set it up8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
A report that compares, per project, the work in progress (WIP) amounts in the project subledger with the WIP balances in the general ledger, for a ledger date range.
What you do here
Use it at month-end or project closure to cross-check project WIP against the ledger before you post or eliminate.
Example
At the October 2026 close BEAT's project accountant sees PRJ-0042 with 4,500.00 of WIP sales value on the project side and 5,000.00 in the ledger; the 500.00 difference is accrued revenue that was not fully reversed at invoicing.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
When to run it
When to run it
At month-end close or at project closure, to cross-check project WIP amounts against the WIP balances in the general ledger.
How often
At each month-end close.
What the output shows
Accrued revenue posted as WIP is reversed at invoicing; when the reversal is incomplete the WIP account keeps a balance. Learn's Accrued revenue reconciliation links back to this report to cross-check detected amounts. The report changes nothing; it only lists amounts.
First ledger date of the postings to include.Checked in Dynamics 365
2026-10-01
To date
Last ledger date of the postings to include.Checked in Dynamics 365
2026-10-31
Project view
Groups the rows of the report, for example by project.Checked in Dynamics 365
Project
Project level
How many levels of subprojects are shown; 0 shows the project level as grouped.Checked in Dynamics 365
0
Skip zero
Leave out rows whose amounts are zero.Checked in Dynamics 365
Yes
Common errors and fixes
Message
What to do
The project side and the ledger side differ for a project.
Look for general journal postings on the same account, a change in ledger posting setup during the period, or postings with a ledger date outside the range; correct project postings with Adjust transactions. Microsoft Learn
Use exactly one closed fiscal period as the ledger date range, after all project postings and Post costs for it are done, with Skip zero on.The report sets the project side next to the ledger side; open postings or a range that cuts a period make timing differences look like errors.
On the live system, Project manager, Project supervisor, Chief executive officer and Chief financial officer can run this page.
Checked in Dynamics 365
Solution architect
5Design impact
Shared or per company
Per legal entity: the report reads only the project data of the company you are signed in to, so run it in each company you close. Checked in Dynamics 365
Can it be undone
Reversible: Running or rerunning the report changes no data.
If you change it later
Accrued revenue posted as WIP is reversed at invoicing; when the reversal is incomplete the WIP account keeps a balance. Learn's Accrued revenue reconciliation links back to this report to cross-check detected amounts. Microsoft Learn
Technical architect
6Technical
Menu item
output:ProjListLedgerReconWIPChecked in Dynamics 365
Form
SysOperationTemplateFormChecked in Dynamics 365
Roles to set it up and use it
To use itProject manager ProjProjectManagerProject supervisor ProjProjectSupervisorChief executive officer CompanyChiefExecutiveOfficerChief financial officer CompanyChiefFinancialOfficerGive people one of these roles. On this system, 4 roles can run this page.Checked in Dynamics 365
Load order: Ledger reconciliation - WIP has no data entity in Data management: it is an SSRS report (design ProjListLedgerRecon) that reads posted project data. There is nothing to migrate for the report itself; load the project data it reads, for example opening balances through Journals > Beginning balance, then run the report in the new system and compare its totals with the old one.Microsoft Learn
Checked in a working Dynamics 365 system, version 10.0.49: the menu item, form, table and security, the page.
To cite this step: PM-RC-280, Set the ledger dates and layout for Ledger reconciliation - WIP. Beyond ERP Atlas Hub, 2026-11-11. https://www.beyonderp.cloud/atlas/step/PM-RC-280