A report that compares, per project, the cost and revenue that projects posted to profit and loss accounts with the balances of those accounts in the general ledger, for a ledger date range.
Project management and accountingInquiries and reportsGeneral ledger reconciliation reports
output:ProjListLedgerReconProfitLoss
Business process
Manage project financials
Menu item
output:ProjListLedgerReconProfitLoss
Setup steps
1 on this page
Show what matters for
PAGE GUIDEWhat the page does and how to use it8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
A report that compares, per project, the cost and revenue that projects posted to profit and loss accounts with the balances of those accounts in the general ledger, for a ledger date range.
What you do here
Use it at period close to tie project profit and loss to the general ledger before you report margins.
Example
For October 2026 BEAT's project accountant finds the project side at 312,880.00 revenue and 198,410.00 cost; the ledger shows 199,010.00 cost, and the 600.00 gap is a manual journal on the project cost account.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
When to run it
When to run it
At period close, after project postings and invoices are complete, to reconcile project profit and loss amounts with the general ledger.
How often
At each period close.
What the output shows
Costs reach profit and loss either directly (profile set to Profit and loss) or later through Post costs (profile set to Balance), and invoiced revenue at invoicing; run Post costs before the reconciliation or the project side and ledger side differ in timing. The report changes nothing; it only lists amounts.
First ledger date of the postings to include.Checked in Dynamics 365
2026-10-01
To date
Last ledger date of the postings to include.Checked in Dynamics 365
2026-10-31
Project view
Groups the rows of the report, for example by project.Checked in Dynamics 365
Project
Project level
How many levels of subprojects are shown; 0 shows the project level as grouped.Checked in Dynamics 365
0
Skip zero
Leave out rows whose amounts are zero.Checked in Dynamics 365
Yes
Common errors and fixes
Message
What to do
The project side and the ledger side differ for a project.
Look for general journal postings on the same account, a change in ledger posting setup during the period, or postings with a ledger date outside the range; correct project postings with Adjust transactions. Microsoft Learn
Use exactly one closed fiscal period as the ledger date range, after all project postings and Post costs for it are done, with Skip zero on.The report sets the project side next to the ledger side; open postings or a range that cuts a period make timing differences look like errors.
On the live system, Project manager, Project supervisor, Chief executive officer and Chief financial officer can run this page.
Checked in Dynamics 365
Solution architect
5Design impact
Shared or per company
Per legal entity: the report reads only the project data of the company you are signed in to, so run it in each company you close. Checked in Dynamics 365
Can it be undone
Reversible: the report changes no data: This report compares project and ledger amounts only; it changes nothing. Microsoft Learn
If you change it later
Costs reach profit and loss either directly (profile set to Profit and loss) or later through Post costs (profile set to Balance), and invoiced revenue at invoicing; run Post costs before the reconciliation or the project side and ledger side differ in timing. Microsoft Learn
Technical architect
6Technical
Menu item
output:ProjListLedgerReconProfitLossChecked in Dynamics 365
Form
SysOperationTemplateFormChecked in Dynamics 365
Roles to set it up and use it
To use itProject manager ProjProjectManagerProject supervisor ProjProjectSupervisorChief executive officer CompanyChiefExecutiveOfficerChief financial officer CompanyChiefFinancialOfficerGive people one of these roles. On this system, 4 roles can run this page.Checked in Dynamics 365
Load order: Ledger reconciliation - profit and loss has no data entity in Data management: it is an SSRS report (design ProjListLedgerRecon) that reads posted project data. There is nothing to migrate for the report itself; load the project data it reads, for example opening balances through Journals > Beginning balance, then run the report in the new system and compare its totals with the old one.Microsoft Learn