About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
Step by step, with screenshots
Set up Multisource policy assignments1 screen
Use this page to set which vendor split applies to each product, and to compare actual purchases with the target split.
Screen 1
Assign the multisource policy to an item
Go to Procurement and sourcing > Setup > Policies > Multisource policy assignments
Select New
Enter the item number (and a site, warehouse or dates if the policy applies only there)
Choose the policy
Select Save
1Item number
BEAT-ITEM-001
Policy
BEAT-SPLIT
Show the full screen page title tab to open what to set or check
Steps from Microsoft
Go to Procurement and sourcing > Setup > Policies > Multisource policy assignments.
Select New, or select an existing assignment and select Edit.
In the Item number field, select the item.
Optionally select a Site and a Warehouse; leave them blank to apply to all.
Enter the From date and To date.
In the Policy field, select the multisource policy.
One assignment per item with Site and Warehouse blank, plus site or warehouse assignments only where the split differs, each with From date and To dateBlank site and warehouse apply the policy everywhere, and when several assignments match a planned order the most specific one wins.
Expecting short-term demand to arrive on time. Vendor calendars aren't considered in multi-vendor sourcing, so the chosen vendor may deliver later than another would; assign a vendor manually for urgent demand.
Feature management and licence
Feature to turn on
Source products and materials from multiple vendors using Planning Optimization (Mandatory, on by default)
Reversible: End an assignment with a To date or edit it; existing planned orders aren't split or reassigned until planning runs again. Microsoft Learn
If you change it later
When more than one assignment matches a planned order, master planning uses the most specific one, such as an assignment that names a warehouse over one that names only a site. Microsoft Learn
Technical architect
6Technical
Menu item
MpsMultiSourcePolicyAssignmentChecked in Dynamics 365
Form
MpsMultiSourcePolicyAssignmentChecked in Dynamics 365
Table
MpsMultiSourcePolicyAssignmentShown as “Multisource policy assignment” in Record infoChecked in Dynamics 365
Data entities
MpsMultiSourcePolicyAssignmentEntityMultisource policy assignment Checked in Dynamics 365
To set it up or change itPurchasing agent VendPurchasingAgentBuying agent TradeBuyingAgentProduction planner ReqProductionPlannerTo use itPurchasing manager TradePurchasingManagerAccounts payable manager VendInvoiceAccountsPayableManagerAuditor AuditPolicyManagerGive people one of these roles. On this system, 6 roles can open this page.Checked in Dynamics 365
Actions on the page
Options: Personalize, Page options, ShareChecked in Dynamics 365
Checked in a working Dynamics 365 system, version 10.0.49: the menu item, form, table and security, the page, the demo records and the values in the screenshots.