Intercompany master planning

A dialog that starts a planning run across several companies in a set order, to calculate requirements and create planned intercompany orders.

Business process
Plan intercompany trade in Dynamics 365 Supply Chain Management
Menu item
InterCompanyReqCalcSchedule
Show what matters for
PAGE GUIDEWhat the page does and how to use it7 sections. Choose a role to highlight what matters to you.
Everyone

1What it is and why

What it isA dialog that starts a planning run across several companies in a set order, to calculate requirements and create planned intercompany orders.
What you do hereUse this dialog to run master planning in each related company, repeated over a number of iterations, so that demand passes along the intercompany chain.
Functional consultant · Solution architect

2Where it fits

End user · Functional consultant

3How to do it

About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.

When to run it

When to run itWhen companies supply each other and demand in a downstream company must reach the supplying company before planners act on it.
How oftenOn demand, or as part of your regular planning cycle when intercompany demand changes.
Batch settingsStart it from one company only, as Microsoft recommends, and run it in the background because each iteration runs master planning in every company of the group.
What the output showsPlanned orders in each company of the planning group, including planned intercompany purchase orders. If the supplying company shows no demand, the firming time fence is usually missing, so no intercompany purchase orders were created and the chain stopped after the first pass.

Source: Microsoft Learn

Steps from Microsoft

  1. Go to Master planning > Master planning > Run > Intercompany master planning.
  2. In Intercompany planning group, select the group of companies to plan. Planning runs in every company of the group, starting from the lowest scheduling sequence.
  3. In Number of intercompany planning iterations, enter how many passes you need. With two companies, the first pass passes demand to the supplying company and the second passes its delays back; up to 30 passes are possible, and each extra pass makes the run longer.
  4. Set First iteration and Subsequent iterations to the update principle to use, for example Regeneration, and enter the Number of threads for parallel planning.
  5. After the run, open Planned orders in each company and look for intercompany purchase demand and the matching planned supply.

Source: Microsoft Learn

Test checklist

  1. Each company in the group has a new plan version after the run.
  2. The supplying company shows the downstream company's demand.
  3. Delays in the supplying company are reflected in the downstream plan after the second pass.

Source: Microsoft Learn

Solution architect

4Design impact

Can it be undonePartly: Run the planning again to replace planned orders. Intercompany purchase and sales orders created by firming are real orders and must be handled in each company. Microsoft Learn
If you change it laterWithout a firming time fence, no intercompany purchase orders are created automatically, so the demand does not pass to the other companies. Microsoft Learn
Technical architect

5Technical

Menu itemInterCompanyReqCalcSchedule Checked in Dynamics 365
Roles to set it up and use itTo use itProduction planner ReqProductionPlannerPurchasing manager TradePurchasingManagerGive people one of these roles. On this system, 2 roles can run this page.Checked in Dynamics 365