TC-PM-SETUP-430 · Test case

Vendor retention held and released by completion

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. Vendor payment retention term with 50/20/0, 80/10/10 and 100/0/100 lines
  2. Term applied to the vendor on the project's Vendor agreements FastTab
Steps
  1. Post a vendor invoice for 50 of 100 units at 300 each
  2. Post a vendor invoice for the next 30 units
  3. Post a vendor invoice for the last 20 units
Expected resultFirst invoice: 3,000 retained, 12,000 payable. Second: 900 retained and 300 released, 8,400 payable. Third: nothing retained and the remaining held amount released.
What should failPost an invoice for a vendor that is not on the Vendor agreements FastTab: nothing is retained.

Setup it checks

Atlas Hub