TC-PM-SETUP-350 · Test case

Cost template drives percentage of completion

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. Fixed-price project with forecast of 100 hours
  2. Cost template with Completion based on = Unit and only hour categories included
Steps
  1. Post 35 hours.
  2. Create revenue recognition for the period with Completion method from cost template.
  3. Review the estimate.
Expected resultPercentage of completion is 35 percent.
What should failWith unplanned hours included and no forecast update, posting more than 100 hours shows the project as 100 percent complete or more before the work is finished.