TC-PM-RB-310 · Test case

Project cash flow dates expected inflows with buffer days

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. Payment terms of 14 days exist.
Steps
  1. Post a project invoice of 10,000.00 for PRJ-0042 dated 31 October 2026 with 14-day payment terms.
  2. Set General buffer days to 3 and Individual buffer days on the contract to 10.
  3. Run Project cash flow with Include expected payment = Yes and check that the 10,000.00 inflow is dated 27 November 2026 (31 October + 14 + 13 days).
Expected resultThe inflow appears on 27 November 2026.
What should failWith Include expected payment = No, the unpaid invoice does not appear.