TC-PM-OPS-100 · Test case

Requisition creates a project commitment

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. The requisition workflow is active.
  2. PRJ-0042 exists.
Steps
  1. Create a requisition for PRJ-0042 for 360.00.
  2. Submit and approve it.
  3. Open committed costs for PRJ-0042.
Expected resultA commitment of 360.00 is listed for the requisition.
What should failA requisition without project ID creates no project commitment.

Setup it checks