TC-MP-PLAN-010 · Test case

Plan time fence overrides the coverage group

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. An item whose coverage group has a coverage time fence of 180 days
  2. A sales order for the item 120 days out
Steps
  1. On the master plan set Coverage to Yes and 90 days
  2. Run master planning
  3. Check planned orders for the item
Expected resultNo planned order is created for the sales order 120 days out, because the plan's 90-day time fence overrides the coverage group.
What should failSet Coverage to No on the plan and rerun: a planned order is created, because the coverage group's 180 days apply.

Setup it checks

Atlas Hub