Project management and accountingPeriodicRevenue recognition
action:ProjControlPeriodPeriodicEliminateV2
Business process
Manage project financials
Menu item
action:ProjControlPeriodPeriodicEliminateV2
Setup steps
1 on this page
Show what matters for
PAGE GUIDEWhat the page does and how to use it8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
A periodic job that eliminates revenue recognition projects and finishes fixed price projects when they reach 100 percent completion.
What you do here
Use it to close revenue recognition: WIP moves to profit and loss for completed contract projects, and accruals are removed for completed percentage projects.
Example
BEAT's fixed price project PRJ-0031 reached 100.00 percent on 09/30/2026 with 182,000.00 of WIP on a completed contract basis. The project accountant eliminates it with Set stage to Finished on: the WIP moves to profit and loss and the project stage becomes Finished.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
When to run it
When to run it
When a fixed price project reaches 100 percent completion.
How often
Once per project, at completion.
Batch settings
Run per period code after the Ready for elimination report.
What the output shows
WIP moved to profit and loss (completed contract) or accruals removed (completed percentage); the status becomes Eliminated.
Elimination stops because non-estimated transactions exist.
Turn on Eliminate with WIP warnings, or check the Allow elimination when non-estimated transactions exist parameters; a project above 100 percent first needs the Set cost to complete to zero method. Microsoft Learn
Test checklist
Find PRJ-0031 in the Ready for elimination report.
Eliminate with Set stage to Finished.
WIP for PRJ-0031 is 0.00 and cost of 182,000.00 is in profit and loss.
Eliminate only projects in the Ready for elimination report, with Set stage to Finished on.The report shows projects at 100 percent; finishing stops late postings.
On the live system, Project manager uses this page.
Checked in Dynamics 365
Solution architect
5Design impact
Shared or per company
Per company: it eliminates revenue recognition projects of the legal entity you run it in. Microsoft data model
Can it be undone
Yes, by reversing: Use Reverse revenue recognition eliminations with the same date. Microsoft Learn
If you change it later
Clears WIP to profit and loss or removes accruals and sets the status to Eliminated; with Set stage to Finished, the project can't take new transactions. Microsoft Learn
Technical architect
6Technical
Menu item
action:ProjControlPeriodPeriodicEliminateV2Checked in Dynamics 365
Form
ProjControlPeriod_EliminateChecked in Dynamics 365
Roles to set it up and use it
To use itProject manager ProjProjectManagerGive people one of these roles. On this system, 1 role can run this page.Checked in Dynamics 365
Load order: Eliminate revenue recognition has no data entity in Data management, and the revenue recognition period table (ProjControlPeriodTable) has none either. Migrate WIP and accrual balances, then create revenue recognition in the target system from the first open period.Microsoft data model