A report of the hours, expenses and items consumed, one row per project category, comparing actual figures with the budget held in a forecast model, built from posted project transactions.
Project management and accountingInquiries and reportsConsumption reports
output:ProjListProjConsumptionCategory2Column
Business process
Analyze project performance
Menu item
output:ProjListProjConsumptionCategory2Column
Setup steps
1 on this page
Show what matters for
PAGE GUIDEWhat the page does and how to use it8 sections. Choose a role to highlight what matters to you.
Everyone
1What it is and why
What it is
A report of the hours, expenses and items consumed, one row per project category, comparing actual figures with the budget held in a forecast model, built from posted project transactions.
What you do here
It answers how much work and material went into each of the project categories, as an actual-against-budget check, so project managers see whether effort runs ahead of plan before it shows in profit. The Project manager, Project supervisor, CEO and CFO roles can run it on this system.
Example
BEAT runs Category consumption (actual vs. budget) against the remaining budget model BUD-REM for 2026. HOURS-CONS has consumed 219.00 hours against 199.00 budgeted, so the project manager asks for a budget revision before more hours are posted.
The page in Dynamics 365. page title tab to open what to set or check
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
When to run it
When to run it
Weekly or at month end, after timesheets and expense journals are posted, at the budget review.
How often
Weekly or monthly
Batch settings
Run it from the dialog for one review, or run it in the background on a monthly recurrence for the close pack.
What the output shows
Hours, expense amounts and item amounts consumed, one row per project category, actual against the budget in the forecast model.
Run the Category consumption (actual vs. budget) report
Review hours, expenses and items consumed per project category comparing actual figures with the budget held in a forecast model.
Steps from Microsoft
Go to Project management and accounting > Inquiries and reports > Consumption reports > Category consumption (actual vs. budget).
Turn on the project types and the Hour, Expense and Item transaction types you want counted for each project category; consumption is about effort, so include Internal and cost projects if internal work matters.
Enter From date, Break date and To date, keep Actual vs. budget on Deviation and pick the Forecast model that holds the consumption budget, for example BUD-ORIG.
Turn on Skip zero so categories with no amounts in the dates drop out, and keep the category list short enough to compare at a glance.
Read the hour quantity and the expense and item amounts on each project category row; compare hours with what was planned before they turn into cost.
Check the hour total against Ledger updates - consumption, then ask for a forecast or budget update for any project category that runs ahead of plan.
Turn on each project type to include; at least one must be on. Time projects post no ledger transactions, so they add hours but no amounts to financial totals.Microsoft Learn
Time and material and Fixed-price on
Include transaction types
Turn on the transaction types to include: hours, expenses and items are what the consumption figures count.Microsoft Learn
Hour, Expense and Item on
(Project date) From date / Break date / To date
The date range, with a break date inside it. With Actual vs. budget set to Sum, actual figures are taken up to the break date and budget figures after it.Checked in Dynamics 365
1 July 2026 / 30 September 2026 / 31 December 2026
(Ledger date) From date / Break date / To date
The date range, with a break date inside it. With Actual vs. budget set to Sum, actual figures are taken up to the break date and budget figures after it.Checked in Dynamics 365
1 July 2026 / 30 September 2026 / 31 December 2026
Forecast model
The forecast model that holds the budget figures. With project budget control, pick the original or remaining budget forecast model that the project's budget uses.Microsoft Learn
BUD-ORIG
Actual vs. budget
Deviation (the default on this dialog) shows actual against budget; Sum adds actual and budget together, split at the break date.Checked in Dynamics 365
Deviation
Skip zero
Leaves out rows where every amount is zero.Checked in Dynamics 365
Yes
Show amount
How amounts are printed: With decimals (the default), without decimals, or in thousands or millions.Checked in Dynamics 365
With decimals
Show hour
Whether hour lines show the number of hours, their cost value or both.Checked in Dynamics 365
Common errors and fixes
Message
What to do
The budget side of every row is zero.
The Forecast model is empty or not the one the budget lives in; with project budget control pick the original or remaining budget forecast model. Microsoft Learn
Test checklist
Run Category consumption (actual vs. budget) for BEAT for October 2026 with HOURS-CONS in the data.
Open Posted project transactions filtered on the same project and dates.
Check that the hour total on the HOURS-CONS row equals the sum of the hour transactions, for example 219.00 hours.
Pick the Forecast model that holds the approved budget first, then the date range and break date; keep Actual vs. budget on Deviation.The deviation is only as good as the model behind it; a wrong or empty model makes every row look over or under budget.
On the live system, Project manager, Project supervisor, Chief executive officer and Chief financial officer can run this report.
Checked in Dynamics 365
Solution architect
5Design impact
Shared or per company
Per legal entity: the report reads the projects, transactions and setup of the company you run it in. Run it in each company to compare them. Checked in Dynamics 365
Can it be undone
Reversible: Reversible: the report changes no data. Checked in Dynamics 365
If you change it later
Rerun after timesheets, expense journals and item journals are posted; the consumption totals change with every posting for the dates. The report itself changes nothing downstream. Microsoft Learn
Technical architect
6Technical
Menu item
output:ProjListProjConsumptionCategory2ColumnChecked in Dynamics 365
Form
SysOperationTemplateFormChecked in Dynamics 365
Roles to set it up and use it
To use itProject manager ProjProjectManagerProject supervisor ProjProjectSupervisorChief executive officer CompanyChiefExecutiveOfficerChief financial officer CompanyChiefFinancialOfficerGive people one of these roles. On this system, 4 roles can run this page.Checked in Dynamics 365
Load order: Category consumption (actual vs. budget) has no data entity in Data management: it is a report. Move the project transactions, timesheets and forecasts it reads, and the report shows them when it runs.Checked in Dynamics 365