BeyondERP.Newsletter
Menu

Setup page · Master planning

Sequences

A setup page where you define sequences, such as paint colour or paint type, and rank their values to set the order in which production is scheduled.

Used by
Materials manager, Production manager
Business process
Plan production
Menu item
PMFSequenceTable
Main table
PMFSequenceTable
Data entity
ProductionOrderSequencingSequenceEntity
Setup steps
1 on this page
Show what matters for
PAGE GUIDEWhat the page does and how to use it8 sections. Choose a role to highlight what matters to you.
Everyone

1What it is and why

What it isA setup page where you define sequences, such as paint colour or paint type, and rank their values to set the order in which production is scheduled.
What you do hereUse this page to create the sequences and ranked values that are assigned to items, so that planned orders can be arranged in a preferred production order.
ExampleFor example, a paint maker gives latex paint rank 0 and enamel paint rank 1 so that latex paint is produced first.
Sequences page in Dynamics 365
The page in Dynamics 365. page title tab to open what to set or check
Functional consultant · Solution architect

2Where it fits

End user · Functional consultant

3How to do it

About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.

Setup steps on this page

Set up Sequences

Use this page to create the sequences and ranked values that are assigned to items, so that planned orders can be arranged in a preferred production order.

Steps from Microsoft

  1. Go to Master planning > Setup > Sequencing > Sequences.
  2. Create a sequence.
  3. In the Sequence ID and Description fields, enter a code and a description.
  4. On the Sequence value FastTab, select New.
  5. In the Value and Rank fields, enter a value and its rank.
  6. Repeat for each additional value.

Source: Microsoft Learn

Fields on the page

FieldWhat it meansTable column
Sequence IDThe code or name of the sequence that is used to sort production.Microsoft Learn SequenceId
DescriptionA description of the sequence.Microsoft Learn Description
ValueA value of the sequence, such as a colour.Microsoft Learn SequenceValue
RankThe rank of the value; the lower the number, the earlier it comes in the sequence.Microsoft Learn SequenceNumber

Test checklist

  1. Create a sequence (for example colour) with ranked values and assign values to test items.
  2. On the master plan set Sequencing to Yes with a time fence in days.
  3. Run master planning, then open Master planning > Master planning > Sequenced planned orders.
  4. Check that start dates follow the ranked values, mark the rows and select Accept.
  5. Open Planned orders and check that order dates now follow the sequence.

Source: Microsoft Learn

Functional consultant

4Setup decisions

Setup stepRecommended value and whyDecision, common mistake and test
Set up SequencesSetting a long Sequencing time fence on the master plan. The longer the time fence, the longer master planning takes to run.
Solution architect

5Design impact

Shared or per companyPer company: each legal entity has its own records. Microsoft data model
Can it be undoneReversible: Sequencing is recalculated on each master planning run and changes planned orders only when accepted on Sequenced planned orders. Microsoft Learn
Technical architect

6Technical

Menu itemPMFSequenceTable Checked in Dynamics 365
FormPMFSequenceTable Checked in Dynamics 365
TablePMFSequenceTableShown as “SEQUENCE” in Record infoChecked in Dynamics 365
Data entitiesProductionOrderSequencingSequenceEntityProduction order sequencing sequences Microsoft data model
Who can open itPrivilegesMaintain sequences PMFSequenceTableMaintainView sequences PMFSequenceTableViewDutiesEnable master scheduling process ReqMasterSchedulingProcessEnable
2 security rolesMaterials manager InventMaterialsManagerProduction manager ProdProductionManager
Checked in Dynamics 365
Roles to set it up and use itTo set it up or change itProduction manager ProdProductionManagerMaterials manager InventMaterialsManagerGive people one of these roles. On this system, 2 roles can open this page.Checked in Dynamics 365
Actions on the page(Action Pane without tabs): Sequence groupChecked in Dynamics 365
Developer

7Developer

Open it by URLhttps://<your-environment>/?mi=PMFSequenceTable
Integrate withProductionOrderSequencingSequenceEntity data entity Microsoft data model
Data migrationProductionOrderSequencingSequenceEntity (Production order sequencing sequences): loaded for each company.Microsoft Learn
Table definitionPMFSequenceTable columns and relations Microsoft data model
Everyone