DEC-PM-SETUP-350 · Design decision
What should Completion based on use for this cost template?
Compare the options before configuring the related setup steps.
Options
AAmount: progress = cost in accounting currency against forecast cost. Reflects all included costs but moves with expense timing.BUnit: progress = quantity (for example hours) against forecast quantity. Stable for labour-driven work but ignores cost rate differences.CStraight line: progress spread evenly between project start and end dates. Simple, ignores actual effort.Recommendation
| Recommendation | Use Unit or Amount on planned hours for labour-driven fixed-price work and keep the forecast current; use Straight line only where revenue should accrue evenly over time. |
|---|---|
| Depends on |
|
| Owner | Finance controller |
Setup steps it affects
Source
| Source | https://learn.microsoft.com/dynamics365/project-operations/revenue-recognition/rev-rec-cost-templates |
|---|