DEC-PM-SETUP-350 · Design decision

What should Completion based on use for this cost template?

Compare the options before configuring the related setup steps.

Options

AAmount: progress = cost in accounting currency against forecast cost. Reflects all included costs but moves with expense timing.
BUnit: progress = quantity (for example hours) against forecast quantity. Stable for labour-driven work but ignores cost rate differences.
CStraight line: progress spread evenly between project start and end dates. Simple, ignores actual effort.

Recommendation

RecommendationUse Unit or Amount on planned hours for labour-driven fixed-price work and keep the forecast current; use Straight line only where revenue should accrue evenly over time.
Depends on
  • Revenue recognition policy
  • Quality of project forecasts
  • Whether expenses are part of measuring progress
OwnerFinance controller

Setup steps it affects

Source

Sourcehttps://learn.microsoft.com/dynamics365/project-operations/revenue-recognition/rev-rec-cost-templates