DEC-MP-PLAN-010 · Design decision
Which scheduling method should the plan use for planned production orders?
Compare the options before configuring the related setup steps.
Options
AOperations scheduling: a general estimate over time; operations are not exploded into jobs.BJob scheduling: each operation is split into jobs with capacity information; detailed, for short-term shop floor planning.Recommendation
| Recommendation | Use operations scheduling for medium and long-term plans, and job scheduling when the plan must schedule individual jobs on the shop floor in the short term. |
|---|---|
| Depends on |
|
| Owner | Production planning manager |
Setup steps it affects
Source
| Source | https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/master-plans |
|---|