DEC-MP-COV-030 · Design decision

Which method should master plans use to reduce forecast requirements?

Compare the options before configuring the related setup steps.

Options

ANone: forecast is never reduced; sales orders create extra planned orders on top of the forecast.
BPercent - reduction key: forecast is multiplied by the key's percentage per period; no link to actual orders.
CTransactions - reduction key: actual demand in each key period consumes the forecast; Percent is ignored, only dates count.
DTransactions - dynamic period: actual orders consume the forecast between one forecast date and the next; no reduction key is needed.

Recommendation

RecommendationChoose C or D when actual orders should consume the forecast; choose D when forecast lines don't follow fixed buckets. Use B only for a planned, time-based fade of the forecast, and A only for simulations.
Depends on
  • Whether forecasts are entered in fixed buckets (week, month)
  • Which transactions count as qualified demand (Reduce forecast by on the coverage group)
OwnerSupply chain planning manager

Setup steps it affects

Source

Sourcehttps://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/reduction-keys