Hold prorates the period

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. A 200.00 monthly line for February
Steps
  1. Apply hold with Adjust schedule Yes and Hold date 10 February.
  2. Remove the hold with Remove date 10 February.
Expected resultFebruary is split into 1 to 9 February at 64.29 and 10 to 28 February at 135.71.
What should failWithout the Remove hold user group override, the user can't remove the hold.