TC-PM-SETUP-340 · Test case

Forecast split by key

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. Key SPLIT-6040.
Steps
  1. Enter a 10,000.00 forecast with the key.
Expected result6,000.00 and 4,000.00 are forecast on the two projects.
What should failA key totalling 90.00 percent leaves 1,000.00 unforecast.

Setup it checks

Atlas Hub