TC-PM-SETUP-330 · Test case

Remaining budget is reduced by actuals

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. Original and Remaining budget models
  2. Approved project budget using both
Steps
  1. Post an hour journal line on the budgeted project
  2. Open Cost control with the original and remaining models selected
Expected resultActual cost increases and Remaining budget decreases by the posted amount; Original budget is unchanged.
What should failSelect a different forecast model on Cost control: the results aren't accurate.