Fixed price projects - profit and loss backlog report shows PRJ-0057

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. Fixed-price revenue project PRJ-0057 with revenue recognition posted for period code MONTH up to 2026-10-31
Steps
  1. Open the report and choose period code MONTH.
  2. Enter estimate date 2026-10-31.
  3. Run the report and find PRJ-0057.
Expected resultPRJ-0057 shows total estimated profit, accumulated profit and the remaining amount, and total minus accumulated equals the remaining amount.
What should failWith Include eliminated projects off an eliminated project is not listed.