Resource payroll allocation (2 periods) shows posted hour cost

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. An approved timesheet with 8.00 hours at a cost price of 40.00 on PRJ-0042, posted on 2026-10-15
Steps
  1. Open the report and select the project type of PRJ-0042.
  2. Enter the October 2026 dates and run the report.
  3. Find the row of the resource and item.
Expected resultEach resource and item shows one amount per period and the totals equal the single-period report run for each range.
What should failWith dates in September 2026 the 320.00 of these hours is not included.

Setup it checks

Atlas Hub