BeyondERP.Newsletter
Menu

TC-PM-RC-060 · Test case

Resource payroll allocation shows posted hour cost

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. An approved timesheet with 8.00 hours at a cost price of 40.00 on PRJ-0042, posted on 2026-10-15
Steps
  1. Open the report and select the project type of PRJ-0042.
  2. Enter the October 2026 dates and run the report.
  3. Find the row of the resource and item.
Expected resultThe report shows the resource and item with the posted hours and their cost value, and the amount equals the credit on the payroll allocation account for those hours.
What should failWith dates in September 2026 the 320.00 of these hours is not included.

Setup it checks

Atlas Hub