Resource/item cash flow dates expected inflows with buffer days
A test you can run to check that the setup below works.
How to run the test
Before you start
Payment terms of 14 days exist.
Steps
Post a project invoice of 10,000.00 for PRJ-0042 dated 31 October 2026 with 14-day payment terms.
Set General buffer days to 3 and Individual buffer days on the contract to 10.
Run Resource/item cash flow with Include expected payment = Yes and check that the 10,000.00 inflow is dated 27 November 2026 (31 October + 14 + 13 days).
Expected result
The inflow appears on 27 November 2026.
What should fail
With Include expected payment = No, the unpaid invoice does not appear.