BeyondERP.Newsletter
Menu

TC-PM-RB-130 · Test case

Project consumption (2 periods) matches the source figures

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. Posted project transactions for October 2026 exist in BEAT.
Steps
  1. Run Project consumption (2 periods) for BEAT for October 2026 with PRJ-0042 in the data.
  2. Open Posted project transactions filtered on the same project and dates.
  3. Check that the hour total on the PRJ-0042 row equals the sum of the hour transactions, for example 215.00 hours.
Expected resultThe report total equals the source figure for the same dates and selections.
What should failWith the Hour transaction type turned off, the hour lines of the source no longer appear on the report.

Setup it checks

Atlas Hub