Imported kWh appear per cost center

A test you can run to check that the setup below works.

How to run the test

Before you start
  1. Imported statistical measures for Electricity processed
Steps
  1. Filter on Electricity and the period.
  2. Read the magnitude per cost center.
Expected resultCC001 shows 2,450.00, CC002 4,100.00 and CC003 15,000.00, as imported.

Setup it checks

Atlas Hub