3How to do it
About the examples: Examples and screenshots in this guide use BEAT, a demo company in a Dynamics 365 test environment. Use your own company's codes and values instead of copying them.
When to run it
When to run it
After backflush costing has run for a period, to review the variances calculated for a production flow.
How often
Once per backflush costing period for each production flow, and on demand when variances look unusual.
What the output shows
The production flow's variances to standard cost on the chosen date, at the level you picked. Backflush costing calculates variances per production flow and period, not per kanban, so a large variance points to the flow's consumption or standard cost for that period.
Nothing to undo: The report only reads backflush costing results; it changes nothing. Microsoft Learn
Technical architect
5Technical
Menu item
output:LeanProductionFlowVariancesChecked in Dynamics 365
Form
SysOperationTemplateFormChecked in Dynamics 365
Roles to set it up and use it