DEC-TA-SETUP-010 · Design decision
How should the cost of paid breaks be charged to production and project jobs (Standard time under Direct payroll costs)?
Compare the options before configuring the related setup steps.
Options
AYes: the break cost goes to the job running in parallel with the paid break. Accurate per job, but the cost lands on whichever job was running.BAllocation: the break cost is spread equally over all jobs registered that day. Smooths cost across jobs.CNo: paid breaks don't increase the hourly cost of jobs. Simple, but job costs exclude break pay.Recommendation
| Recommendation | Choose Allocation when breaks should be shared across the day's work, Yes when the parallel job should carry it, and No only when break pay is costed elsewhere. |
|---|---|
| Depends on |
|
| Owner | Cost controller with the production manager |
Setup steps it affects
Source
| Source | https://learn.microsoft.com/dynamics365/supply-chain/production-control/pay-based-on-registrations |
|---|