Should projects be controlled with forecasts or with budgets?

Compare the options before configuring the related setup steps.

Options

AProject forecasting: unit-based lines with every transaction attribute, submodels allowed, but no approval or audit trail on changes.
BProject budgeting: amount-based by category and activity, original and remaining budget models, workflow approval and revision history.

Recommendation

RecommendationUse budgeting when finance needs controlled, approved amounts and an audit trail; use forecasting when project managers plan operationally by units, workers and items.
Depends on
  • Need for approval of budget changes
  • Level of detail needed in plans
  • Overrun control required
OwnerProject controller