DEC-OA-RES-020 · Design decision

How do you tell resources with the same capability but different proficiency apart?

Compare the options before configuring the related setup steps.

Options

ASeparate capabilities (for example Low-speed drilling and High-speed drilling): simple to read, but more capabilities to maintain.
BOne capability with a Level per resource and a Minimum level needed on the route requirement: fewer records, needs levels kept up to date.

Recommendation

RecommendationUse Level when proficiency is a measurable scale; use separate capabilities when the activities are really different.
Depends on
  • How routes express requirements
  • Whether Priority is used as Primary resource selection in Scheduling parameters
OwnerProduction planner with the production engineer

Setup steps it affects