At what level should Landed cost post value adjustments to the ledger (Posting specification)?

Compare the options before configuring the related setup steps.

Options

ATotal: one total figure is posted. Least detail in the ledger.
BItem group: the adjustment is split per item group.
CItem number: the adjustment is split per item. Most detail, more ledger lines.

Recommendation

RecommendationChoose Item number when finance needs to trace landed cost adjustments to items; Item group or Total when summary posting is enough. Agree it once, because the setting is shared by all legal entities.
Depends on
  • Level of ledger analysis finance needs
  • Ledger volume tolerance
  • Agreement across all legal entities that use Landed cost
OwnerFinance controller with the supply chain lead

Setup steps it affects

Source

Sourcehttps://learn.microsoft.com/en-us/dynamics365/supply-chain/landed-cost/landed-cost-parameters#costing-fasttab