DEC-AM-PM-010 · Design decision
Which interval type should a time-based plan line use?
Compare the options before configuring the related setup steps.
Options
ARepeated from plan date: fixed calendar interval (for example lubrication every week), whatever happened before.BRepeated from last work order: counts from the actual end of the last completed work order with the same job type, variant and trade, so a late job pushes the next one.CRepeated from start date: counts from the start date on the asset or functional location relation.Recommendation
| Recommendation | Use Repeated from plan date for fixed-calendar jobs and Repeated from last work order for inspections that should be about one interval apart; use counter lines where wear follows usage. |
|---|---|
| Depends on |
|
| Owner | Maintenance planner |